In 2011, Tres Cruces bus station and shopping center undertook an important extension project that incorporated 26,498 m 2 to the center’s super built-up area.
The project was developed by the firm Luis E. Lecueder, which trusted Ingener with the electrical installation for the cinemas and the rest of the center, as well as with the ventilation and air conditioning systems.
The air conditioning system involved the full execution of a 1,200 TR chilled water system; the erection of four 300 TR cooling towers, central stations; the assembly of over 30 tons of ducts, pipes, control and automation system, etc.
As regards the electrical assembly, the landmarks were the complete construction of a medium voltage substation; the construction of over 80,000 m of conductors; the installation of over 3,000 light fixtures and the erection of more than 40 switchboards.
TRES CRUCES 2012 UPGRADE – ELECTRIC; HVAC
Montevideo, Uruguay, 2012/2013