GAMESA

COLONIA ARIAS WIND FARM – 70MW

This wind farm, located in the department of Flores, consist of 35 2 MW wind turbines, totaling an installed power capacity of 70 MW and generating 300 GMh annually.
For this project, Gamesa entrusted Ingener with the detailed engineering, the complete construction of the MV internal network, mounting and connection of switchgears for the wind turbines and the EPC of the step-up substation, utility substation and connection to the 150 kV transmission network.